GOAL 2: Complete Odor Control Facilities at the Ryder Street Treatment Plant

 

Unfortunately, disagreeable odors are synonymous with wastewater treatment and the District's plant on Ryder Street is no exception. We have been working hard during the past few years to improve the quality of the air leaving the Ryder Street Treatment Plant and are in the final phase of a project to build odor control facilities. This goal was developed to ensure that planned odor control facilities are designed and constructed by the end of 2004.

 When    Who What Status Comments

Done

On Target Rev
By December 1, 2004


 

 

the District Manager and Finance Director will finalize funding for the odor control facilities.     Will go to bid in February.
At the February 2005 Board meeting


 
the District Manager and Director of Operations will present to the Board for their consideration a construction contract for the odor control facilities.     Will open bids in March and present at next available Board meeting.
By March 15, 2005 the District Manager will ensure start of construction of the Secondary Odor Control Project     Anticipate Notice to Proceed issued in April.

 