HISTORY
The Vallejo Sanitation and Flood Control
District was created by a special act of
the California State Legislature in
1952. This act was put forward by the
City of Vallejo and Solano County for a
service area that encompassed
approximately 23 square miles, most of
it unincorporated county land. Our
current service area is approximately 26
square miles, 90% of it incorporated
into the
City of Vallejo.
WASTEWATER
TREATMENT
Since its inception, the District has
worked to improve the quality of
wastewater discharges to the Carquinez
and Mare Island Straits. In 1952,
untreated sewage and stormwater flowed
through a common piping system and were
discharged into the Mare Island Strait
at 14 different locations. |
|
 |
By 1959, the
District's first wastewater treatment plant was
brought on line, greatly reducing the amount of
untreated sewage discharged to the Mare Island
Strait. Sewage flows through pipes to our modern
wastewater treatment plant at 450 Ryder Street
in southwestern Vallejo. The plant has a dry
weather capacity of 15.5 million gallons per day
(mgd) and a wet weather capacity of 60 mgd.
WASTEWATER SYSTEM IMPROVEMENTS
Early 1970s
The original 1959 plant was designed to treat
sewage only to a primary level, clarifying the
wastewater by removal of material by settlement
and skimming. In 1972, new regulations from the
U.S. Environmental Protection Agency
necessitated the construction of a secondary
treatment plant. Secondary treatment removes the
biological elements remaining in wastewater
after primary treatment.
1977 - 1985
Vallejo's secondary facility was completed in
1977. During initial efforts to bring the new
plant on-line, it became obvious that the plant
was not going to work properly. The plant used
an innovative physical/chemical process, hailed
at the time by federal and state regulators as
the "process of the future." In 1981, this
process was declared a failure by the regulators
who once praised it.
In 1985, after considerable legal battling and
political effort, the federal and state
governments acknowledged their responsibility to
assist in correcting the failed plant.
1988 - Present
A new secondary facility was completed in 1988,
which included a trickling filter/solids contact
biological treatment process, a new operations
building, and additional chlorination and
de-chlorination disinfecting facilities.
The new plant
uses the same process that nature does to clean
water in streams and rivers. Once the water is
cleaned and returned to the Bay, the dried
biosolids that are left are treated and used as
a soil amendment and fertilizer at the
District-owned Tubbs Island farm in Sonoma
County.
Secondary
treatment dramatically improves the plant's
effluent quality. To address long-term
wastewater treatment needs, the District
developed a 20-year Master Plan for wastewater
capital facilities that included a program to
eliminate wet weather sewage overflows to
surface waters entering San Francisco Bay. This
effort involved the construction of new wet
weather treatment facilities at the existing
wastewater treatment plant as well as
improvements to the District's collection
system. The new plant facilities were brought on
line in 1991. These improvements increased the
plant's capacity from 30 mgd to 60 mgd during
wet weather flows. The District also increased
the size of several pipes within the collection
system between 1988 and 1995. In 1992, an
Inflow/Infiltration Control Program was
prepared. The District currently follows this
program as a means to reduce the entrance of
rainwater into the sanitary sewer system.
SANITARY SEWER
OVERFLOWS
Pipes that carry wastewater to the plant are
made out of various materials ranging from clay
and cement to materials made of paper and tar
called Orangeburg that were installed during
World War II. Over time, tree roots and ground
settling can cause the pipes to develop small
cracks that allow excess rainwater and ground
water to flow in. Wastewater flows can increase
from an average of 13 million gallons per day in
dry weather to 60 million gallons per day during
heavy rains. The District is currently in the
process of implementing a $60 million program to
make the system repairs and improvements
necessary to eliminate overflows.
STORM DRAIN SYSTEM
The District has also made improvements to the
storm drainage system. There are more than 150
miles of pipes and channels, as well as four
pump stations that provide drainage in the
Vallejo area. The District maintains these storm
drains. Severe flooding in the Vallejo area has
been reduced substantially. Major facilities
constructed include Lake Dalwigk and Austin
Creek in the 1950s, and facilities below Lake
Chabot Dam in the late 1980s and early 1990s.
Engineers use a formula to measure the intensity
and quantity of rain that falls during a storm.
Each storm is given a rating that is measured by
"years." A 15-year storm means that the area is
likely to experience a storm of similar capacity
only once in 15 years. Likewise a 100-year storm
means that a similar storm would be expected in
the area only once in 100 years. The District
has a minimum capacity requirement for new
drainage systems. New public systems must have a
capacity to convey the 15-year storm design.
Since 1988, if the area drained is one square
mile or larger, the required capacity is
conveyance for a 100-year storm. The District
continues to follow the Storm Drain Master Plan
prepared in 1987 and updated in 2003. |